Commercial solar
If your business wants the federal commercial solar tax credit, the one decision that matters is whether your project "begins construction" by July 4, 2026 — here's exactly what that phrase means, why a June 2026 court ruling just changed the rules again, and how to lock the date.
Updated June 30, 2026 · 10 min read
The short answer: if your business wants the federal solar tax credit, the single decision that matters is whether your project "begins construction" by July 4, 2026. Lock that date in, and the Section 48E credit — 6% at the base rate, up to 30% with the right conditions, and up to 50% with both bonus adders — follows your project even if the panels don't switch on for years. Miss it, and you're on a much tighter clock: placed in service by December 31, 2027, or you get nothing.
One thing to clear up before anything else: the commercial credit survived the One Big Beautiful Bill Act (OBBBA, signed July 4, 2025). That's different from the residential homeowner credit (Section 25D), which ended for expenditures made after December 31, 2025 — a cash- or loan-buying homeowner who finishes installing in 2026 gets $0 federal credit. This article is strictly about the business credit, which is alive but on a deadline.
If you want to know whether your roof or land can realistically hit the date, start with a free feasibility estimate to size both the system and the credit.
The federal Clean Electricity Investment Credit (Section 48E) is not a flat 30%. It's a stack, and where your project lands on that stack depends on a handful of conditions. Per the IRS:
Here's the part most commercial owners miss: you don't necessarily need PWA to get to 30%. Under the "One Megawatt Exception," a facility with a maximum net output of less than 1 megawatt (measured in alternating current, based on nameplate capacity) is exempt from the prevailing wage and apprenticeship requirements and still qualifies for the full increased rate. Most commercial rooftops fall under 1 MW — which means most commercial rooftops can reach 30% without the PWA paperwork.
| What you qualify for | Rate | Condition |
|---|---|---|
| Base credit | 6% | Default, no conditions met |
| Increased credit | 30% | Meet prevailing wage + apprenticeship, OR be under 1 MW AC (the One Megawatt Exception) |
| + Domestic content adder | +10 pts → up to 40% | Use qualifying domestic steel, iron, and manufactured products |
| + Energy community adder | +10 pts → up to 50% | Located in a designated energy community (verify the current map) |
A note on thresholds, because two numbers get confused constantly: 1 MW is the PWA-exemption threshold (the One Megawatt Exception). 1.5 MW is a separate, now-litigated threshold for one of the begin-construction methods (more on that below). They are different rules. Don't conflate them.
OBBBA was signed into law on July 4, 2025. It set a one-year clock on the wind and solar credits: the credits terminate for facilities that begin construction after July 4, 2026.
That produces two clean outcomes, and almost everything about your timeline depends on which side of the line you land on. Per RSM's analysis of the rules:
That four-year continuity safe harbor is the prize. Per Notice 2025-42, section 4.04, a facility is deemed to satisfy the continuity requirement if it's placed in service within four calendar years after the year construction began. In practice: begin in 2026, and you have until the end of 2030 to finish. That's a world of difference from the December 2027 backstop.
| Begin by July 4, 2026 | Begin after July 4, 2026 | |
|---|---|---|
| Placed-in-service deadline | None fixed — rely on continuity | Hard stop: Dec 31, 2027 |
| Realistic completion window | ~4 years (in service by end of 2030 if begun in 2026) | ~18 months |
| Risk level | Lower — generous runway | High — permitting + interconnection can eat the whole window |
This is the error to avoid above all others: do not assume the December 31, 2027 deadline applies to a project that began on or before July 4, 2026. It doesn't. These two timelines are easy to conflate, so it's worth confirming which one applies to your project.
This is where good intentions go to die. "Begin construction" has a specific legal meaning, and a deposit isn't it. There are two recognized ways to prove you've begun.
You start physical work of a significant nature. Per Notice 2025-42, this is about real, physical activity:
What does not count: planning, designing, securing permits, arranging financing, conducting surveys, or clearing the site. Those are preliminary activities, and the IRS explicitly excludes them. There's no minimum dollar threshold for the Physical Work Test — what matters is the nature of the work, not its cost.
You incur at least 5% of the total project cost. "Incur" has its own technical meaning — a refundable deposit alone generally doesn't cut it — but the principle is straightforward: put real money into the project's hard costs and you've planted your flag on the calendar.
Either test, satisfied on or before July 4, 2026, locks your begin-construction date. But which one you should rely on is, right now, a live legal question.
Here's the freshest and most important fact in this entire piece — and it's barely weeks old.
Last August, Notice 2025-42 killed the 5% Safe Harbor for all wind projects and for solar projects over 1.5 MW, leaving the Physical Work Test as the only way for those larger projects to begin construction. (It kept the 5% option only for low-output solar of 1.5 MW or less.)
Then, on June 6, 2026, a federal court threw that out. The U.S. District Court for the District of Columbia vacated Notice 2025-42 in its entirety, holding that the IRS had acted "arbitrarily and capriciously" under the Administrative Procedure Act, and the court applied the vacatur to all taxpayers — not just the plaintiffs. The practical effect: the 5% Safe Harbor is restored for projects of all sizes.
So is the 5% method back on the table? Today, yes. But this is an unsettled situation. The government can appeal or the IRS can issue new guidance, and the legal commentary expressly cautions taxpayers to "consider the possibility of future IRS guidance or a successful appeal." An appellate process could easily run past the July 4, 2026 deadline — meaning a project that relied on the 5% method for a large facility could find the ground shifting underneath it.
The takeaway is simple. The Physical Work Test survives no matter how the litigation ends. It was valid before Notice 2025-42, it was valid during it, and it's valid now. If you can plausibly start physical work of a significant nature by July 4, the Physical Work Test is the bulletproof path. The 5% Safe Harbor is available today and genuinely useful — but for larger projects it's legally contested, so treat it as the riskier option.
The most expensive misunderstanding is thinking a deposit or a signed design contract is enough. It isn't. A deposit alone generally doesn't satisfy the 5% Safe Harbor's "incurred" standard, and permitting, engineering, and financing don't satisfy the Physical Work Test. You can do all three and still not have "begun construction" in the eyes of the IRS.
Continuity matters too. You can't do a token amount of work, plant your flag, and then sit idle for years. The four-year continuity safe harbor protects you only if the project is actually placed in service within that window.
And the calendar is unforgiving. Permitting and utility interconnection queues routinely take many months to well over a year. A project that hasn't started procurement yet is the one most at risk — not just of missing the July 4, 2026 begin-construction date, but of blowing past the December 2027 backstop too. The runway is shorter than it looks.
The domestic content (+10 pts) and energy community (+10 pts) adders can push a project to as high as 50%. They're worth chasing. But the energy community adder comes with a footnote you can't skip.
Energy community statistical-area designations are redrawn periodically — updated based on the latest unemployment and fossil-employment data. Per the U.S. Treasury, a parcel that qualifies this year may not qualify next year. So never bank the +10 energy-community adder for a specific address without checking it against the current Treasury/IRS map for your site. The adder is real; the eligibility is a moving target.
The commercial 48E credit applies to agricultural operations too — a barn roof or a field array can qualify on the same terms as any commercial project. If that's you, the farm-specific guidance walks through it.
One caution, though: don't build your 2026 financing plan around a USDA REAP grant. USDA paused REAP grant awards in 2026 while it rewrites the program rules. REAP guaranteed loans remain open, but the grant money isn't there this year. Plan around the 48E credit and the loan, not the grant.
The window is real and it's closing. Here's the practical checklist:
If you only do one thing this month, run the numbers. A free feasibility estimate tells you whether a July 4 begin-construction date is realistic for your site — and what the credit is actually worth before you commit a dollar.
For the full picture on every 2026 federal and state incentive, see the 2026 solar incentives guide and the best states for solar.
This article is general information, not tax or legal advice. The begin-construction rules are technical and, as of June 2026, actively litigated — confirm your specific situation with a qualified tax advisor before relying on any credit. See our disclosures for more.
Educational content, not tax, financial, or legal advice. Figures are current as of the update date above; verify with a qualified professional before acting.
For the federal commercial credit (Section 48E), the key deadline is to BEGIN CONSTRUCTION by July 4, 2026. Projects that begin construction on or before that date keep the credit even if they finish later — they rely on a four-year continuity window rather than a fixed completion date. Projects that begin construction after July 4, 2026 must be placed in service by December 31, 2027. The homeowner credit (Section 25D) is separate and already ended for expenditures made after 2025.
There are two ways to prove it. The Physical Work Test means starting physical work of a significant nature — pouring footings, installing racking, or having a manufacturer build custom components under a binding contract — not planning, permitting, or financing. The 5% Safe Harbor means incurring at least 5% of total project cost. As of a June 6, 2026 federal court ruling that vacated IRS Notice 2025-42, the 5% method is available again for all project sizes, but it's being litigated and the government may appeal, so the Physical Work Test is the safer choice for larger projects.
It can be. The Section 48E base rate is 6%, and it rises to 30% if you meet prevailing wage and apprenticeship rules OR if your facility is under 1 megawatt of AC output (the One Megawatt Exception, which covers most commercial rooftops). You can add up to 10 percentage points each for using qualifying domestic content and for being in a designated energy community — potentially reaching a total of 50%.
If you begin construction on or before July 4, 2026, you are not bound by the December 31, 2027 placed-in-service cutoff. Instead you rely on the IRS continuity safe harbor: place the project in service within four calendar years after the year you began. So a project that begins construction in 2026 generally needs to be operating by the end of 2030.
No. OBBBA (signed July 4, 2025) ended the residential homeowner credit (Section 25D) for expenditures made after 2025, but the commercial Clean Electricity Investment Credit (Section 48E) survived. What changed is the timing: businesses now have to begin construction by July 4, 2026 to lock in the credit on the most favorable terms, which is why 2026 is a now-or-maybe-never year for commercial solar.
Free, no obligation, and sourced from the IRS, USDA, and EIA.